Coastal site at the wind-power heartland of Finland with outstanding grid capacity, scaling to 500MW.
Public Status
Project developers —
Location
Site size (ha) 240
Local population —
Area overview —
Free-cooling hours / yr 7955
Population within 50 km 41133
Hot days / yr (>25 °C) —
Cold days / yr (<-10 °C) —
Daylight (solstice) —
Time zone —
Nearest HV substation —
Substation distance (km) —
Grid carbon (gCO₂/kWh) —
Industrial elec. price (€/MWh) —
Grid mix —
Distance to peering hubs Frankfurt: 1558 km · Stockholm: 373 km · London: 1757 km · Amsterdam: 1472 km
Zoning status Reservation agreement out for municipal signature (Feb 2026). Zoning approval targeted Nov/Dec 2026.
Avg annual temp (3 yr) 6 °C
-10° -5° 0° 5° 10° 15° 20° Apr Jul Oct 2024 Apr Jul Oct 2025 Apr Jul Oct 2026 Apr 20 °C max · -9 °C min
Power
Power source Mixed Clean
Initial MW 60
Target MW 500
Max capacity (MW) 500
Power notes —
Power availability (public text) —
Connection voltage 110kV & 400kV
PPA status (public) —
Heat reuse Planned
Design
IT load (MW) 400-640
Design PUE 1.15
Rack density (kW) 40-70 kW (Air) / 132-400 kW (DLC)
Cooling Air — perimeter; DLC — room-level CDU
Workload mix Training & later cloud / inference
Connectivity
Fibre providers Elisa
Fibre speeds (Gbps) 400G DWDM (dual/protected)
Latency to key markets Frankfurt ~17–31 ms · London ~31–35 ms · NY ~95–105 ms.
Fibre commentary GlobalConnect brief report indicates fibre connectivity sufficient. Telia 400G DWDM proposal: OTC €385k, MRC €6,180/mo.
Timeline
Ready-to-build date —
Energisation date —
Narrative
News & press —
Project description (long) Brought to Scale42 March 2025. Out-bid other developers for a 500 MW+ facility. Strong municipal backing through extensive stakeholder engagement and multiple site visits. Large expanse of dense woodland with undulating topography, situated next to a main highway.