Frankfurt: 1966 km · Stockholm: 914 km · London: 1967 km · Amsterdam: 1772 km
Zoning status
Zoning being changed from LNF to industry (with data centre) with political support. Working with ABO Plan & Arkitektur on detailed zoning. Permits expected to be approved at or shortly after zoning.
vs. Frankfurt baseline
Avg temp
2.6 °C-8.8 °C vs FRA
Free-cooling
8,378 h/yr+4,178 h vs FRA
Grid carbon
—
Industrial price
—
Avg annual temp (3 yr)2.6 °C
17 °C max · -13 °C min
Power
Power source
Primarily Hydro
Initial MW
50
Target MW
50
Max capacity (MW)
50
Power notes
—
Power availability (public text)
—
Connection voltage
22kV
PPA status (public)
Under negotiation
Heat reuse
Planned
Design
IT load (MW)
40-80
Design PUE
1.15
Rack density (kW)
40-70 kW (Air) / 132-400 kW (DLC)
Cooling
Air — perimeter; DLC — room-level CDU
Workload mix
Training & possibly inference
Connectivity
Fibre providers
Telenor, Telia, GlobalConnect, Nordlandsnett
Fibre speeds (Gbps)
Up to 400G per wavelength (DWDM), scalable
Latency to key markets
Oslo ~8–12 ms · Stockholm ~10–15 ms · Frankfurt ~25–30 ms · Amsterdam ~25–30 ms · London ~30–35 ms.
Fibre commentary
Served via Nordlandsnett with access to Telenor, Telia and GlobalConnect. Strong for northern Norway; final allocation and route diversity to be locked down. International reach indirect via Sweden/Denmark into DANICE / IRIS — not a cable-landing location.
Timeline
Ready-to-build date
—
Energisation date
—
Narrative
News & press
—
Project description (long)
Identified by Scale42 in 2021; in zoning approval process since identification and land option. Undulating greenfield site in the centre of a valley with a mix of grassland and natural woodland. "50 MW allocated; 50 MW+ expansion potential".